UPDATE - Aztec Circle Drive Temporary Impacts (Near GMCS) - From 06/12/2023 to 07/14/2023
Jun 12Trenching and underground utility work will require vehicular access on the portion of Aztec Cir Dr to the East of the Engineering building to be limited to one lane. Vehicular thru-traffic will be maintained by flagmen directing traffic in alternating directions. Additionally, parking spaces located to the West of the GMCS building will be temporarily closed and not accessible throughout the duration of work. The work will require temporary sidewalk closures and alternate paths may require access through EIS. Alternate pedestrian/accessible paths will be delineated by signage, flagmen and traffic control. Please be advised that work will result in localized dust and noise.
Facilities Services North Driveway and Loading Area Impacts - From 05/29/2023 to 06/09/2023
May 29Trenching and underground utility work that requires vehicular access on a portion of the driveway north of Facility Services (FS) will be reduced to a single lane impacting through traffic during active construction hours. Steel plates will be added to accommodate access to COGEN and Facilities Services as needed. Alternate vehicular traffic will be delineated by signage, flagmen and traffic control. Please be advised that work will result in localized dust and noise.
Planetarium Court Temporary Minor Construction Impacts - From 05/29/2023 to 06/09/2023
May 29Trenching and underground utility work will require a minor localized detour to pedestrian paths in the Planetarium Court located between Physical Science and Physics and Astronomy. Pedestrian paths will be delineated by signage, flagmen and traffic control. Please be advised that work will result in localized dust and noise.
Aztec Circle Drive Temporary Impacts (Near Atkinson Hall) - From 05/22/2023 to 06/16/2023
May 22Trenching and underground utility work will require vehicular access on a portion of Aztec Circle Drive to the East of Atkinson Hall to be limited to one lane throughout the duration of work. Vehicular thru-traffic will be maintained by flagmen directing traffic in alternating directions and alternate pedestrian/accessible paths will be delineated by signage, flagmen and traffic control. Please be advised that work will result in localized dust and noise.
Aztec Circle Drive Temporary Impacts (Near Facilities Services) - From 05/22/2023 to 06/02/2023
May 22Trenching and underground utility work will require vehicular access on a portion of Aztec Circle Drive to the North of the Art North (Art N) building to be limited to one lane throughout the duration of work. Vehicular thru-traffic will be maintained by flagmen directing traffic in alternating directions and alternate pedestrian/accessible paths will be delineated by signage, flagmen and traffic control. Please be advised that work will result in localized dust and noise.
Aztec Circle Drive Laydown Areas (Near Engineering Interdisciplinary Science) - From 05/15/2023 to 02/05/2025
May 15Laydown areas will temporarily experience construction traffic with loading/unloading of materials which may periodically impede the use of driveways and parking spaces in the driveway between Engineering & Interdisciplinary Sciences (EIS) and Physics buildings, the driveway to the Northeastern corner of the GMCS building. Every effort will be made to maintain clear access as much as possible.
Facilities Services North Driveway and Loading Area Impacts - From 05/08/2023 to 12/30/2023
May 8Designation of laydown areas will eliminate use of parking spaces and generate construction traffic for loading/unloading of materials in the driveway and loading area north of the Facilities Services (FS) building. Vehicular thru-traffic will be maintained in one direction delineated by construction fencing, signage, and traffic control.
UPDATE - Facilities Services North Driveway and Loading Area Impacts - From 05/08/2023 to 06/06/2024
May 8The designation of laydown areas and construction of New Substation A will eliminate use of parking spaces and generate construction traffic for loading/unloading of materials in the driveway and loading area north of the Facilities Services (FS) building. The ADA accessible parking stall on the north driveway will not be available. ADA parking and access to the building will be maintained at the south entrance of Facilities Services. ADA access to the Granger Loading Dock through the Exterior Wheelchair Lift located on the north driveway may be periodically unavailable throughout the construction duration. To coordinate access, please reach out to Alejandro Rivera at 858.248.5739 or [email protected].
Closure of Parking Spaces in Lot 16 - 05/08/2023 - 04/30/2025
May 8Closure of multiple parking spaces in a portion of the Northern corner of Lot 16. Along with the installation of construction trailers and construction fencing, a portion of the lot will require pavement restriping and signage to redirect vehicular traffic flow.
Aztec Bookstore (BOOK) - On 07/19/2022
Jul 19Investigation of motor control center affecting users of Aztec Bookstore (BOOK) from 7:30 AM to 9:30 AM on July 19th, 2022.