Upcoming Impacts
Administration Building Outage – On 3/26/2025
Mar 26As part of the campus electrical upgrades project, a planned electrical outage for the building is required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outage will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be either unplugged or powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please note that the outage only impacts systems and equipment not supported by the emergency generator. Any equipment plugged into designated outlets supported by the emergency generator will only experience a brief interruption. Also note that the building will be closed to the public throughout the outage window detailed below. **
Engineering Parking Lot – From 3/17/2025 to 3/21/2025
Mar 17As part of the campus electrical upgrades project, heating hot water will be temporarily unavailable during the interruption window noted below. Please be aware that affected buildings may experience cooler than normal temperatures during this time.
Engineering – From 3/17/2025 to 3/21/2025
Mar 17As part of the campus electrical upgrades project, heating hot water will be temporarily unavailable during the interruption window noted below. Please be aware that affected buildings may experience cooler than normal temperatures during this time.
Administration, Art (I) South, Art (II) North, Arts and Letters, Atkinson Hall, Aztec Bookstore, Building A, Bioscience Center, Charles B. Bell Jr. Pavilion, Chemical Sciences Lab, Education, Engineering, Engineering & Interdisciplinary Sciences, Facilities Services Boiler Shop, Faculty Staff Club, Geology Math and Computer Science, Hardy Tower, Hazmat Building, Hepner Hall, Life Sciences North, Life Sciences South, Lot 16, Marquee Sign, Nasatir Hall, North Education, Physics, Physics-Astronomy, Physical Sciences, Professional Studies and Fine Arts, and Storm Complex – On 3/13/2025
Mar 13Occupants should be aware that redundancy in the power feed will be temporarily unavailable for buildings served by Substation A. In the event of a power loss during the maintenance period, emergency generators will continue to supply power to emergency circuits. The project team has a restoration plan in place, anticipated to take less than 30 minutes. While the likelihood of interruptions is low, it is recommended that any sensitive equipment be shut down in advance as a precaution.
Administration, Art (I) South, Art (II) North, Arts and Letters, Atkinson Hall, Aztec Bookstore, Building A, Bioscience Center, Charles B. Bell Jr. Pavilion, Chemical Sciences Lab, Education, Engineering, Engineering & Interdisciplinary Sciences, Facilities Services Boiler Shop, Faculty Staff Club, Geology Math and Computer Science, Hardy Tower, Hazmat Building, Hepner Hall, Life Sciences North, Life Sciences South, Lot 16, Marquee Sign, Nasatir Hall, North Education, Physics, Physics-Astronomy, Physical Sciences, Professional Studies and Fine Arts, and Storm Complex – 04/03/2025
Mar 13Occupants should be aware that redundancy in the power feed will be temporarily unavailable for buildings served by Substation A. In the event of a power loss during the maintenance period, emergency generators will continue to supply power to emergency circuits. The project team has a restoration plan in place, anticipated to take less than 30 minutes. While the likelihood of interruptions is low, it is recommended that any sensitive equipment be shut down in advance as a precaution.
Administration, Art (I) South, Art (II) North, Arts and Letters, Atkinson Hall, Aztec Bookstore, Building A, Bioscience Center, Charles B. Bell Jr. Pavilion, Chemical Sciences Lab, Education, Engineering, Engineering & Interdisciplinary Sciences, Facilities Services Boiler Shop, Faculty Staff Club, Geology Math and Computer Science, Hardy Tower, Hazmat Building, Hepner Hall, Life Sciences North, Life Sciences South, Lot 16, Marquee Sign, Nasatir Hall, North Education, Physics, Physics-Astronomy, Physical Sciences, Professional Studies and Fine Arts, and Storm Complex – Postponed
Mar 13Occupants should be aware that redundancy in the power feed will be temporarily unavailable for buildings served by Substation A. In the event of a power loss during the maintenance period, emergency generators will continue to supply power to emergency circuits. The project team has a restoration plan in place, anticipated to take less than 30 minutes. While the likelihood of interruptions is low, it is recommended that any sensitive equipment be shut down in advance as a precaution.
Life Science North Building Outage – On 02/06/2025
Feb 6: As part of the campus electrical upgrades project, a planned electrical outage for the building is required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outage will entail a total loss of power for the duration specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please note that the outage only impact systems and equipment not supported by the emergency generator. Any equipment plugged into designated outlets supported by the emergency generator will only experience a brief interruption. Also note that the building will be closed to the public throughout the outage window detailed below. **
Engineering Building Outage – On 02/06/2025
Feb 6As part of the campus electrical upgrades project, a planned electrical outage for the building is required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outage will entail a total loss of power for the duration specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification.
UPDATE - Cogeneration Plant, Facilities Services (FS), FS Boiler Shop Building Outage – On 02/05/2025
Feb 5As part of the campus electrical upgrades project, a short planned electrical outage for the buildings is required. The outage will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window.
Cogeneration Plant, Facilities Services (FS), FS Boiler Shop Building Outage – On 01/31/2025
Jan 31As part of the campus electrical upgrades project, a short planned electrical outage for the buildings is required. The outage will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window.