Current Impacts
Engineering - From 04/01/2024 to 07/26/2024
Apr 1Please be advised that the end date and time for the work have been extended. In addition to all previously communicated information, a portable construction restroom will be installed in front of room 122D for construction personnel. Any work within specific occupied spaces will continue to be coordinated with room users prior to the work taking place.
Engineering - From 04/01/2024 to 04/12/2024
Apr 1Work associated with setting up temporary power will necessitate construction personnel to occupy rooms 101E, 103, 103B, 103C, 104, 118, 118A, 122B, 123A, 130, 132A, 202G, 325 throughout the duration of work. Please be advised that work will result in localized dust and noise, but there are no anticipated impacts to any building systems.
Life Sciences South - From 02/26/2024 to 02/28/2024
Feb 26Installation of fire alarm conduits will necessitate construction personnel to occupy electrical rooms 195 and 195A throughout the duration of work. Work will not cause any shutdown or outages to any building systems. Please be advised that work will result in localized dust and noise.
UPDATE - Closure of Extended Parking Spaces in Lot 16 - From 12/18/2023 to 12/31/2024
Dec 18In addition to the initially communicated closure in Lot 16, the area closed to parking will be increased.
Loss of Redundancy in Power Generation - From 10/19/2023 to 10/20/2023
Oct 19Occupants need to be aware that there will be no redundancy to the power feed for the listed facilities. Should a loss of power occur during the maintenance period, emergency generators will still provide power to emergency circuits. Although the likelihood of a power interruption during this maintenance period is low, it is recommended that any sensitive equipment be shut down prior to the scheduled maintenance period.
Aztec Circle Drive Laydown Areas (Near Engineering Interdisciplinary Science) - From 05/15/2023 to 02/05/2025
May 15Laydown areas will temporarily experience construction traffic with loading/unloading of materials which may periodically impede the use of driveways and parking spaces in the driveway between Engineering & Interdisciplinary Sciences (EIS) and Physics buildings, the driveway to the Northeastern corner of the GMCS building. Every effort will be made to maintain clear access as much as possible.
UPDATE - Facilities Services North Driveway and Loading Area Impacts - From 05/08/2023 to 06/06/2024
May 8The designation of laydown areas and construction of New Substation A will eliminate use of parking spaces and generate construction traffic for loading/unloading of materials in the driveway and loading area north of the Facilities Services (FS) building. The ADA accessible parking stall on the north driveway will not be available. ADA parking and access to the building will be maintained at the south entrance of Facilities Services. ADA access to the Granger Loading Dock through the Exterior Wheelchair Lift located on the north driveway may be periodically unavailable throughout the construction duration. To coordinate access, please reach out to Alejandro Rivera at 858.248.5739 or [email protected].
Closure of Parking Spaces in Lot 16 - 05/08/2023 - 04/30/2025
May 8Closure of multiple parking spaces in a portion of the Northern corner of Lot 16. Along with the installation of construction trailers and construction fencing, a portion of the lot will require pavement restriping and signage to redirect vehicular traffic flow.