Upcoming Impacts
Marquee Sign On 11/15/2024 and 11/21/2024
Nov 15As part of the campus electrical upgrades project, planned electrical outages for the Marquee Sign and Parking Lot 16 are required. The outage will entail a total loss of power for the duration specified below, affecting electrical power to the Marquee Sign. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification.
REMINDER - Building A - On 11/15/2024
Nov 15As part of the campus electrical upgrades project, a planned electrical outage for the building is required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outage will entail a total loss of power for the duration specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be unplugged or powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please note that the building will be closed to the public throughout the outage window detailed below. **
Building A - On 11/15/2024
Nov 15As part of the campus electrical upgrades project, a planned electrical outage for the building is required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outage will entail a total loss of power for the duration specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be unplugged or powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please note that the building will be closed to the public throughout the outage window detailed below. **
UPDATE - Life Sciences North (LSN) - Building Outages - On 11/14/2024
Nov 14As part of the campus electrical upgrades project, planned electrical outages for the building are required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outages will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please note that the outages only impact systems and equipment not supported by the emergency generator. Any equipment plugged into designated outlets supported by the emergency generator will only experience a brief interruption. Also note that the building will be closed to the public throughout the outage windows detailed below. **
Canyon Crest Drive Lane Closure and Lot 16 Parking - From 11/14/2024 to 11/18/2024
Nov 14A portion of Canyon Crest Drive for vehicular traffic west-bound will be limited to one lane, but thru-traffic will be maintained. Signage will be posted, and flaggers will direct traffic around the lane closure. Additionally, a small number of parking spaces near Building A in Parking Lot 16 will be temporarily closed. Please be advised that the work may result in localized dust and noise.
REMINDER II - Life Sciences North (LSN) - Building Outages - On 11/12/2024
Nov 12As part of the campus electrical upgrades project, planned electrical outages for the building are required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outages will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please note that the outages only impact systems and equipment not supported by the emergency generator. Any equipment plugged into designated outlets supported by the emergency generator will only experience a brief interruption. Also note that the building will be closed to the public throughout the outage windows detailed below. **
REMINDER - Life Sciences North (LSN) - Building Outages - On 10/24/2024 and 11/12/2024
Nov 12As part of the campus electrical upgrades project, planned electrical outages for the building are required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work. The outages will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please note that the outages only impact systems and equipment not supported by the emergency generator. Any equipment plugged into designated outlets supported by the emergency generator will only experience a brief interruption. Also note that the building will be closed to the public throughout the outage windows detailed below. **
GMCS Parking Spaces - From 11/12/2024 to 12/31/2024
Nov 12A portion of Canyon Crest Drive for vehicular traffic west-bound will be limited to one lane, but thru-traffic will be maintained. Signage will be posted, and flaggers will direct traffic around the lane closure. Additionally, a small number of parking spaces near Building A in Parking Lot 16 will be temporarily closed. Please be advised that the work may result in localized dust and noise.
Aztec Circle Drive Traffic and Parking Lot 16 - From 11/08/2024 to 04/08/2025
Nov 8The re-routing of 12kV cables will require vehicular traffic on the northern corner of Aztec Circle Drive near the Engineering Building to be intermittently limited to one alternating thru-lane for both directions of travel. Traffic will be directed by signage, flagmen and traffic control. Additionally, there will be periodic closures affecting the parking stalls behind the GMCS building and a small number of parking spaces in Lot 16. Please be advised that the work may generate localized dust and noise, although no utility outages are expected.
REMINDER II - Hepner Hall (HH) and Faculty/Staff Center (FSC) - Building Outages - On 10/15/2024, 11/07/2024, and 11/21/2024
Nov 7As part of the campus electrical upgrades project, a planned electrical outage for the Hepner Hall and Faculty/Staff Center buildings is required. There will be periodic construction personnel traffic in and around the buildings throughout the entire duration of the work. The outage will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window. After the outage, users will be able to re-enter the buildings and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification. ** Please also note that the Hepner Hall and Faculty/Staff Center Buildings will be closed to the public throughout the outage windows detailed below. ** Duration of Impacts: The outage schedule is as follows: 1. On Tuesday, October 15th, 2024, from 4:00 am to 6:00 am 2. On Thursday, November 7th, 2024, from 3:30 am to 7:30 am 3. On Tuesday, November 21st, 2024, from 3:30 am to 7:30 am