Upcoming Impacts

All-Campus
  • Electrical Infrastructure Upgrade Notification

    Aztec Circle Drive - On 01/24/2025

    Single lane closure in a portion of Aztec Circle Drive to safely remove the SDG&E pole parallel to GMCS and existing substation A. Thru traffic will be maintained. Please heed the directions and instructions of signage and flaggers in the area.

  • Electrical Infrastructure Upgrade Notification

    Aztec Cir Drive – From 01/20/2025 to 01/24/2025

    Medium voltage cable pulling work will limit vehicular access on Aztec Circle Drive, parallel to the Geology, Mathematics, and Computer Science (GMCS) to a single lane throughout the duration of work. Vehicular thru-traffic will be maintained by flagmen directing traffic in alternating directions. In addition, 4 accessible parking spots parallel to the Atkinson Hall building will be closed to provide a safe working space for the construction personnel. Alternate accessible parking spots are located between the Physics Astronomy and Administration Buildings, as shown in Green. Please reference the SDSU 3D Map for Accessible Parking Locations. No building system outages are anticipated as a result of this work.

  • Electrical Infrastructure Upgrade Notification

    Aztec Cir Drive – From 01/20/2025 to 01/24/2025

    Medium voltage cable pulling work will limit vehicular access on Aztec Circle Drive, parallel to the Geology, Mathematics, and Computer Science (GMCS) to a single lane throughout the duration of work. Vehicular thru-traffic will be maintained by flagmen directing traffic in alternating directions. In addition, 4 accessible parking spots parallel to the Atkinson Hall building will be closed to provide a safe working space for the construction personnel. Alternate accessible parking spots are located between the Physics Astronomy and Administration Buildings, as shown in Green. Please reference the SDSU 3D Map for Accessible Parking Locations. No building system outages are anticipated as a result of this work.

  • Electrical Infrastructure Upgrade Notification

    Tree Removal behind GMCS and Lane Closure on Canyon Crest Drive - From 12/19/2024 to 01/17/2025

    The re-routing of high-voltage power lines on the hillside between GMCS and Canyon Crest Drive will necessitate the removal of several trees. The removal of trees is being timed to avoid disturbance of any nesting activities of birds that may occasionally inhabit the surrounding areas. In compliance with SDSU’s practices, replacement trees will be planted elsewhere on campus to enhance the environment of the campus’ wildlife and human community. The work will impact vehicular traffic through Canyon Crest Drive so that a portion of the outside east-bound lane will be temporarily closed. However, thru-traffic will be maintained. Additionally, pedestrian traffic through the hillside ramp between Canyon Crest Drive and GMCS will be closed permanently. Pedestrian access to campus will remain available via the accessible route through the Chemical Sciences Lab elevator to the 5th floor. Vehicular and pedestrian traffic will be directed by signage, flagmen and traffic control. Please be advised that the work may generate localized dust and noise, although no utility outages are expected.

  • Electrical Infrastructure Upgrade Notification

    Canyon Crest Drive Lane Closure and Lot 16 Parking - From 11/14/2024 to 11/18/2024

    A portion of Canyon Crest Drive for vehicular traffic west-bound will be limited to one lane, but thru-traffic will be maintained. Signage will be posted, and flaggers will direct traffic around the lane closure. Additionally, a small number of parking spaces near Building A in Parking Lot 16 will be temporarily closed. Please be advised that the work may result in localized dust and noise.

  • Electrical Infrastructure Upgrade Notification

    Aztec Circle Drive Traffic and Parking Lot 16 - From 11/08/2024 to 04/08/2025

    The re-routing of 12kV cables will require vehicular traffic on the northern corner of Aztec Circle Drive near the Engineering Building to be intermittently limited to one alternating thru-lane for both directions of travel. Traffic will be directed by signage, flagmen and traffic control. Additionally, there will be periodic closures affecting the parking stalls behind the GMCS building and a small number of parking spaces in Lot 16. Please be advised that the work may generate localized dust and noise, although no utility outages are expected.

  • Electrical Infrastructure Upgrade Notification

    Avenue of the Arts and Aztec Circle Drive - From 10/22/2024 to 10/25/2024

    The demolition of existing underground medium voltage cables will require vehicular traffic on Avenue of the Arts and the northern corner of Aztec Circle Drive to be intermittently limited to one alternating thru-lane for both directions of travel. Traffic will be directed by signage, flagmen and traffic control. Additionally, there will be periodic closures affecting a minimal number of parking stalls behind the GMCS building and in Parking Lot 16. Please be advised that the work may generate localized dust and noise, though no utility outages are expected.

  • Electrical Infrastructure Upgrade Notification

    Mediterranean Garden - From 10/10/2024 to 12/12/2024

    Construction personnel will need to occupy Electrical Room 13 for the duration of the work. Additionally, construction traffic will occur within Room 10SE within the Hepner Hall building basement. Please note that this work may generate localized dust and noise. Efforts will be made to coordinate dust/noise impacts around occupied room schedules.

  • Electrical Infrastructure Upgrade Notification

    Loss of Redundancy in Power Generation - All Campus - On 10/10/2024

    Occupants should be aware that normal cogeneration redundancy will be temporarily unavailable for the full campus. Although the likelihood of a utility interruption during this maintenance period is low while the campus is utilizing power from SDG&E, it is recommended that any sensitive equipment be shut down prior to the scheduled maintenance period in an abundance of caution.

  • Electrical Infrastructure Upgrade Notification

    UPDATE - Loss of Redundancy in Power Generation - All Campus - On 10/10/2024

    Occupants should be aware that normal cogeneration redundancy will be temporarily unavailable for the full campus. Although the likelihood of a utility interruption during this maintenance period is low while the campus is utilizing power from SDG&E, it is recommended that any sensitive equipment be shut down prior to the scheduled maintenance period in an abundance of caution.