UPDATE - Loss of Redundancy in Power Generation - All Campus - On 10/10/2024

Update 10/10/2024: Please note that the duration for the disconnection of cogeneration redundancy is required to be extended until further notice. An update will be provided when more information is available. All other impacts remain as previously communicated.

New end date for impacts: TBD (Originally Thursday, October 10th, 2024, at 1:00 pm)

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Original Notification (Published 10/03/2024):

Electrical Infrastructure Upgrades Project

Loss of Redundancy in Power Generation

To: All Campus Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Cogeneration redundancy for the full campus will be disconnected to enable a safe working environment for the construction crew. The campus gas turbine generators will not be available during the loss of redundancy. SDG&E will continue to supply power to the campus.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Occupants should be aware that normal cogeneration redundancy will be temporarily unavailable for the full campus. Although the likelihood of a utility interruption during this maintenance period is low while the campus is utilizing power from SDG&E, it is recommended that any sensitive equipment be shut down prior to the scheduled maintenance period in an abundance of caution.

Start Time / Date: Thursday, October 10th, 2024, at 3:30 am

End Time / Date: Thursday, October 10th, 2024, at 1:00 pm

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].