Aztec Cir Drive – From 01/20/2025 to 01/24/2025

Updated 01/23/2025: Please be advised that the end date and time for the work have been extended. All other impacts remain as originally communicated.

New end date for duration of impacts:

End Time / Date: 05:00 PM, Friday, January 31, 2025

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Electrical Infrastructure Upgrades Project
Aztec Circle Drive - Partial Road Closure 

and Accessible Parking Closure near Atkinson Hall

image

To: All Campus Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Pull obsolete underground electrical cables in association with building electrical upgrades.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.  

Anticipated Impacts:

Medium voltage cable pulling work will limit vehicular access on Aztec Circle Drive, parallel to the Geology, Mathematics, and Computer Science (GMCS) to a single lane throughout the duration of work. Vehicular thru-traffic will be maintained by flagmen directing traffic in alternating directions. In addition, 4 accessible parking spots parallel to the Atkinson Hall building will be closed to provide a safe working space for the construction personnel. Alternate accessible parking spots are located between the Physics Astronomy and Administration Buildings, as shown in Green. Please reference the SDSU 3D Map for Accessible Parking Locations.

No building system outages are anticipated as a result of this work.

Start Time / Date: 06:00 AM, Monday, January 20, 2025 

End Time / Date: 05:00 PM, Friday, January 24, 2025

*Please note that temporary traffic impacts will be in effect only during construction work hours between the hours of 6:00 am and 5:00 pm. At the end of the work day, traffic impacts will be cleared for normal access and reinstalled the next work day. 

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].