Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Staging of construction materials for electrical upgrades at the Life Sciences South (LSS) building and installation of temporary transformer location.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.  

Anticipated Impacts: Due to ongoing electrical upgrades in the Life Sciences South (LSS), construction trucks and equipment will intermittently park near the Vegetation Garden between LSN and LSS. Construction fencing housing the temporary transformer will be set up near the existing electrical enclosure at LSS. Please be advised that work will result in localized dust and noise. 

Start Time / Date: 6:00 am, Monday, October 7th, 2024

End Time / Date: 5:00 pm, Friday, December 13th, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].