Cogeneration Plant, Facilities Services (FS), FS Boiler Shop – Building Outage - 10/10/2024

To: Cogeneration Plant, Facilities Services (FS), FS Boiler Shop Building Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Relocate SDG&E meters from existing Substation A to new substation A.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: As part of the campus electrical upgrades project, a short planned electrical outage for the buildings is required. The outage will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window.  

Start Time / Date: Thursday, October 10th, 2024, at 5:30 am

End Time / Date: Thursday, October 10th, 2024, at 5:45 am 

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Categorized As