REMINDER III - Donald P. Shiley Bioscience Center (BSCI) - Building Outages - On 10/24/2024

Reminder 10/10/2024: This serves as our 14-day advance notice reminder for the third scheduled outage in the Donald P. Shiley Bioscience Center Building on October 24th, 2024, as originally posted. Please note that there are no changes to the previously communicated outages within the building.

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Electrical Infrastructure Upgrades Project
Donald P. Shiley Bioscience Center (BSCI) – Planned Electrical Outages REMINDER II

Reminder 10/04/2024: This serves as our 14-day advance notice reminder for the second scheduled outage in the Donald P. Shiley Bioscience Center Building on October 18th, 2024, as originally posted. Please note that there are no changes to the previously communicated outages within the building.

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Electrical Infrastructure Upgrades Project
Donald P. Shiley Bioscience Center (BSCI) – Planned Electrical Outages REMINDER 

Reminder 09/16/2024: This serves as our 14-day advance notice reminder for the scheduled outages in the Donald P. Shiley Bioscience Center Building on September 30th, 2024, October 18th, 2024, and October 24th, 2024. Please note that there are no changes to the previously communicated outages within the building.

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Original Notification (Published 08/30/2024):

Electrical Infrastructure Upgrades Project

Donald P. Shiley Bioscience Center (BSCI) – Planned Electrical Outages

To: Donald P. Shiley Bioscience Center (BSCI) Building Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Install temporary power and upgrade the electrical infrastructure throughout the buildings.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: As part of the campus electrical upgrades project, a set of planned electrical outages for the building is required. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work.

The outage will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window.  

After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification.

** Please note that the outage only impacts systems and equipment not supported by the emergency generator. Any equipment plugged into designated outlets supported by the emergency generator will only experience a brief interruption. Please also note that the Donald P. Shiley Bioscience Center will be closed to the public throughout the outage window detailed below. **

Duration of Impacts: The outage schedule is as follows:

  1. On Monday, September 30th, 2024, from 3:30 am to 7:30 am
  2. On Friday, October 18th, 2024, from 3:30 am to 7:30 am
  3. On Thursday, October 24th, 2024, from 3:30 am to 7:30 am

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Categorized As