POSTPONED - Adams Humanities, Aztec Student Union, Children's Center, Cuicacalli Hall, Lamden Hall, Love Library, Love Library Addition, Manchester Hall, Oat Concession #1, Oat Concession #2, Oat Ticket Office, Parking 1, Parking 3, Parking 4, Parking 6, Student Services East, Student Services Garage, Student Services West, Tacuba Hall, Tenochca Hall, Tepeyac Hall, Tula Community Center, Zura Hall, Lot 2, Lot 2a, Lot 2b, Lot 2c, Lot 4a, Lot 17, and Lot 17c – 12/20/2024

Update 12/20/2024: The testing of newly installed and upgraded controls servicing the cogeneration plant and the buildings supported by Substation B will be rescheduled, and an updated notification will be sent out closer to the new date.

New Duration of Impacts: 
Start Time / Date: TBD
End Time / Date: TBD

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Original Notification (Published 12/05/2024:)

Notice for Loss of Redundancy in Power Generation – Substation B

To: Adams Humanities, Aztec Student Union, Children's Center, Cuicacalli Hall, Lamden Hall, Love Library, Love Library Addition, Manchester Hall, Oat Concession #1, Oat Concession #2, Oat Ticket Office, Parking 1, Parking 3, Parking 4, Parking 6, Student Services East, Student Services Garage, Student Services West, Tacuba Hall, Tenochca Hall, Tepeyac Hall, Tula Community Center, Zura Hall, Lot 2, Lot 2a, Lot 2b, Lot 2c, Lot 4a, Lot 17, and Lot 17c Occupants

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Testing of newly installed and upgraded controls servicing the cogeneration plant and buildings supported by Substation B.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Please be aware that ongoing testing in the cogeneration plant may result in up to three brief utility service interruptions within the timeframe indicated below. In the unlikely scenario where an interruption may occur, each interruption would not be expected to last longer than 20 minutes at a time.  While the likelihood of interruptions is low, we recommend frequently saving your work, shutting down or unplugging sensitive equipment, and scheduling any critical tasks that cannot tolerate an interruption outside the testing window as a precaution.

If you have questions or would like more details about potential impacts and recommended measures to prepare for potential utility impacts, please use the contact information provided below.

Duration of Impacts:

Start Time / Date: 7:00 am, Friday, December 20th, 2024

End Time / Date: 2:30 pm, Friday, December 20th, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Categorized As