Administration, Art (I) South, Art (II) North, Arts and Letters, Atkinson Hall, Aztec Bookstore, Building A, Bioscience Center, Charles B. Bell Jr. Pavilion, Chemical Sciences Lab, Education, Engineering, Engineering & Interdisciplinary Sciences, Facilities Services Boiler Shop, Faculty Staff Club, Geology Math and Computer Science, Hardy Tower, Hazmat Building, Hepner Hall, Life Sciences North, Life Sciences South, Lot 16, Marquee Sign, Nasatir Hall, North Education, Physics, Physics-Astronomy, Physical Sciences, Professional Studies and Fine Arts, and Storm Complex Building – 12/19/2024

To: Administration, Art (I) South, Art (II) North, Arts and Letters, Atkinson Hall, Aztec Bookstore, Building A, Bioscience Center, Charles B. Bell Jr. Pavilion, Chemical Sciences Lab, Education, Engineering, Engineering & Interdisciplinary Sciences, Facilities Services Boiler Shop, Faculty Staff Club, Geology Math and Computer Science, Hardy Tower, Hazmat Building, Hepner Hall, Life Sciences North, Life Sciences South, Lot 16, Marquee Sign, Nasatir Hall, North Education, Physics, Physics-Astronomy, Physical Sciences, Professional Studies and Fine Arts, and Storm Complex Occupants

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Testing of newly installed and upgraded controls servicing the cogeneration plant and buildings supported by Substation A.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Please be aware that ongoing testing in the cogeneration plant may result in up to three brief utility service interruptions within the timeframe indicated below. In the unlikely scenario where an interruption may occur, each interruption would not be expected to last longer than 20 minutes at a time.  While the likelihood of interruptions is low, we recommend frequently saving your work, shutting down or unplugging sensitive equipment, and scheduling any critical tasks that cannot tolerate an interruption outside the testing window as a precaution.

If you have questions or would like more details about potential impacts and recommended measures to prepare for potential utility impacts, please use the contact information provided below.

Duration of Impacts:

Start Time / Date: 7:00 am, Thursday, December 19th, 2024

End Time / Date: 2:30 pm, Thursday, December 19th, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.