Adams Humanities, Dramatic Arts, Ellen Ochoa Pavilion, Extended Studies Center Music, Student Services East, Student Services West, Prebys Stage and Parking 6 - On 11/02/2024
Update 10/29/2024: Please note that a planned electrical outage will affect Prebys Stage and Parking 6 in addition to the buildings listed in the original notification. This outage is required as part of the ongoing work detailed below. All other impacts remain as originally communicated.
New List of Impacted Areas: Adams Humanities, Dramatic Arts, Ellen Ochoa Pavilion, Extended Studies Center Music, Student Services East, Student Services West, Prebys Stage and Parking 6
For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.
Original Notification (Published 10/18/2024):
Electrical Infrastructure Upgrades Project
Planned Electrical Outage – Substation D Relay Installation
To: Adams Humanities, Dramatic Arts, Ellen Ochoa Pavilion, Extended Studies Center, Music, Student Services East, Student Services West
From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst
Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:
Scope of Work: Install Substation D relay and upgrade associated controls.
Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.
Anticipated Impacts: As part of the campus electrical upgrades project, a planned electrical outage for the buildings is required.
The outage will entail a total loss of power for the duration specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be unplugged or powered down the day before to avoid unanticipated impacts to the equipment during the outage window.
After the outage, users will be able to re-enter the building and confirm that power is restored, and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification.
** Please note that the outage only impacts systems and equipment not supported by the emergency generator. Any equipment plugged into designated outlets supported by the emergency generator will only experience a brief interruption. Please also note that the building will be closed to the public throughout the outage window detailed below. **
Start Time / Date: 5:00 am, Saturday, November 2nd, 2024
End Time / Date: 12:00 pm, Saturday, November 2nd, 2024
Contact: Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].