Avenue of the Arts & Bioscience Breezeway - From 10/21/2024 to 11/26/2024

image

To: Art I South (Art S), Life Sciences North (LSN), Donald P. Shiley Bioscience Center (BSCI), and Engineering (ENG) Building Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Staging of construction materials for electrical upgrades at the Life Sciences North building.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Due to ongoing electrical upgrades in Life Sciences North, construction restrooms and equipment will be temporarily staged near the SDSU Art Gallery along Avenue of the Arts. Construction trucks and equipment will intermittently park in the parking lot adjacent to the Bioscience Center and the Engineering Building. Construction personnel will occupy the Electric Yard at the end of the Bioscience Breezeway and intermittently park in the vendor stalls. Please be advised that work will result in localized dust and noise.

Start Time / Date: 06:00 AM, Monday, October 21, 2024

End Time / Date: 05:00 PM, Tuesday, November 26, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.