Art II North, Engineering and New Substation A - On 08/06/2024

To: Art II North, Engineering and New Substation A Building Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Pretesting of newly installed fire alarms in the respective electrical and mechanical rooms within the buildings.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Pretesting of newly installed fire alarms in the respective electrical and mechanical rooms within the buildings.

Start Time / Date: 05:00 AM, Tuesday, August 6, 2024

End Time / Date: 07:00 AM, Tuesday, August 6, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Categorized As