Loss of Redundancy in Power Generation - Sub C&D - On 08/01/2024

To: Arena Ticket Office, Aztec Aquaplex, Aztec Recreation Center, Bernstein/Little Theatre, Calpulli Health Center, Calpulli Parking Garage, Chapultepec Hall, Communication, Dramatic Arts, Ellen Ochoa Pavilion, Exercise and Nutritional Sciences, Exercise and Nutritional Sciences Annex, Extended Studies Center, Extended Studies Center Garage, Fowler Athletics Center, Gateway Center, Grounds Area A Building, Grounds Office Trailer, Hilltop Way, Huaxyacac, International Student Center, International Student Center Addition A, International Student Center Addition B, International Student Center Annex, Jeff Jacobs Jam Center, KPBS Radio / TV, Logistical Services, Lot 10, Lot 10A, Lot 11, Lot 13, Lot 5, Lot 6B, Lot 8, Lot 9, Lot 9A, Main Chiller Plant, Music, Parking 12, Parking 15, Parking 6, Parking 6A, Parking 7, Parking 7, Parma Payne Goodall Alumni Center, Peterson Gymnasium, Racquetball Courts, Scripps Cottage, Scripps Cottage Street Lighting String, Softball Field, South Campus Plaza North, South Campus Plaza Parking Garage, South Campus Plaza South, Speech, Language, and Hearing Sciences, Tennis Center, Tennis Locker Rooms, Tony Gwynn Stadium, University Police - UPD, and Viejas Arena

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Cogeneration redundancy for Substations C and D will be disconnected to enable a safe working environment for the construction crew. The campus gas turbine generators and SDG&E will continue to supply power to the campus.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Occupants need to be aware that we will not have our normal cogeneration redundancy for Substations C and D, and that any SDG&E loss of power during this time frame will affect the buildings listed above. Although the likelihood of a utility interruption during this maintenance period is low, it is recommended that any sensitive equipment be shut down prior to the scheduled maintenance period.

Duration of Impacts:

Start Time / Date:   August 1st, 2024, at 6:00 am

End Time / Date:      August 1st, 2024, at 2:00 pm

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.