Loss of Redundancy in Power Generation - Sub B - On 08/01/2024

To: Adams Humanities, Aztec Student Union, Children's Center, Cuicacalli Hall, Lamden Hall, Love Library, Love Library Addition, Manchester Hall, Oat Concession #1, Oat Concession #2, Oat Ticket Office, Parking 1, Parking 3, Parking 4, Parking 6, Student Services East, Student Services Garage, Student Services West, Tacuba Hall, Tenochca Hall, Tepeyac Hall, Tula Community Center, Zura Hall, Lot 2, Lot 2a, Lot 2b, Lot 2c, Lot 4a, Lot 17, Lot 17c occupants

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Cogeneration redundancy for Substation B will be disconnected to enable a safe working environment for the construction crew. The campus gas turbine generators and SDG&E will continue to supply power to the campus.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Occupants need to be aware that we will not have our normal cogeneration redundancy for Substation B, and that any SDG&E loss of power during this time frame will affect the buildings listed above. Although the likelihood of a utility interruption during this maintenance period is low, it is recommended that any sensitive equipment be shut down prior to the scheduled maintenance period.

Duration of Impacts:

Start Time / Date:   August 1st, 2024, at 6:00 am

End Time / Date:      August 1st, 2024, at 2:00 pm

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Categorized As