Planetarium Court Electrical Yard - From 07/22/2024 to 08/02/2024

To: Administration, Physics, Physics Astronomy, Physical Sciences Building Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Concrete pour for transformer pad within the electrical yard.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: The concrete pour for the transformer pad located in the electrical yard in Planetarium Court will result in minor impacts including presence of construction personnel, localized dust and noise. However, there are no major impacts to pedestrians or anticipated outages to any building systems.

Start Time / Date: 06:00 AM, Monday, July 22, 2024

End Time / Date: 04:00 PM, Friday, August 2, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.