Facilities Services North Driveway and Loading Area - On 06/29/2024

Impact notification:

image

To: Facilities Services Building Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Construction clean up and slurry coat of the Facilities Services North Driveway.

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: A portion of Facilities Services North Driveway will be closed to vehicular access throughout the duration of work outlined below. Please also note that work will result in localized dust and noise. 

Start Time / Date: 06:00 AM, Saturday, June 29, 2024 

End Time / Date:   04:00 PM, Saturday, June 29, 2024 

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Categorized As