UPDATE - Art II North - Planned Electrical Outages - 06/10, 06/24, 07/03, and 07/19

Update 06/03/2024:  Please note that the dates for the planned electrical shutdowns have changed. All other details as previously communicated remain the same.  

Updated Duration of Impacts:  The outage schedule is as follows:

  • 2nd Floor Outages:
    1. Monday, June 10th, 2024, between 3:30 am and 7:30 am
    2. Thursday, June 27th, 2024, between 3:30 am and 7:30 am
    3.  Friday, July 19th, 2024, between 3:30 am and 7:30 am (previously Monday, July 22nd)
  • 3rd Floor Outages:
    1. Monday, June 10th, 2024, between 3:30 am and 5:30 am
    2. Wednesday, July 3rd, 2024, between 3:30 am and 7:30 am (previously Friday, July 5th)
    3. July 19th, 2024, between 3:30 am and 7:30 am (previously Monday, July 22nd)

For more details about this impact, please visit the website. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website

Reminder 05/28/2024:  This serves as our 14-day advance notice reminder for the outages scheduled to start on June 10th, 2024.  Please note that there are no changes to the previously communicated outages within the Art II North building. 

For more details about this impact, please visit the website .  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Original Notification (Published 05/10/2024):

Impact notification:

To: Art II North Building Users

From: Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Install temporary power and upgrade the electrical infrastructure throughout the building. 

Reason for Project: Work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts:

As part of the campus electrical upgrades project, a series of electrical outages for the building is required. The outages will impact the 2nd and 3rd floors. There will be periodic construction personnel traffic in and around the building throughout the entire duration of the work.

The outages will entail a total loss of power for the durations specified below, affecting systems such as heating and air, lighting, receptacle convenience power, card/access/access control, elevators, etc. It is highly recommended that sensitive equipment unable to withstand an outage should be powered down the day before to avoid unanticipated impacts to the equipment during the outage window.  

After each outage, users will be able to re-enter the building and confirm that power is restored and systems are fully functional. Any issues should be communicated immediately to the project team using the contact information provided at the end of this notification.

**Please also note that the building will be closed to the public throughout the outage windows detailed below. **

Duration of Impacts:  The outage schedule is as follows:

  • 2nd Floor Outages:
    1. Monday, June 10th, 2024, between 3:30 am and 7:30 am
    2. Thursday, June 27th, 2024, between 3:30 am and 7:30 am
    3. Monday July 22nd, 2024, between 3:30 am and 7:30 am
  • 3rd Floor Outages:
    1. Monday, June 10th, 2024, between 3:30 am and 5:30 am
    2. Friday, July 5th, 2024, between 3:30 am and 7:30 am
    3. Monday July 22nd, 2024, between 3:30 am and 7:30 am

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.