UPDATE - Art II North - From 04/30/2024 to 08/07/2024

Updated 05/10/2024:  There will be a portable restroom/wash station, and a debris box installed in the parking area near Aztec Circle Drive next to room 106C for use by construction personnel. Any work within specific occupied spaces will continue to be coordinated with room users prior to the work taking place.  All other information as previously communicated remains unchanged.  

image

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Original Notification (Published 04/30/2024):

Electrical Infrastructure Upgrades Project
Art II North Building Make Ready Work

To: Art II North Building Users

From:    Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Prepare the building to receive temporary power by installing anchors and racks for temporary power cables inside equipment rooms.  Temporary cable runs will also require access to ceiling spaces in rooms in some areas. 

Reason for Project: Preliminary work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Work will require construction personnel to occupy rooms equipment rooms 200, 200A, 318, and 318A, as well as ceiling spaces in rooms 104, 104A, 104B, 202, 202C, 202D, and 206 throughout the duration of work. Please be advised that work will result in localized dust and noise, but there are no anticipated impacts to any building systems. Any work within specific occupied spaces will continue to be coordinated with room users prior to the work taking place.

Start Time / Date: 06:00 AM, Tuesday, April 30, 2024

End Time / Date: 03:00 PM, Wednesday, August 7, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Categorized As