UPDATED - Engineering - From 04/01/2024 to 08/02/2024

Updated 07/08/2024:  Please be advised that the end date and time for the work have been extended. All other impacts remain as originally communicated.

New end date for duration of impacts:

End Time / Date:      03:00 PM, Friday, August 2, 2024

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Updated 04/12/2024: Please be advised that the end date and time for the work has been extended. In addition to all previously communicated information, a portable construction restroom will be installed in front of room 122D for construction personnel. Any work within specific occupied spaces will continue to be coordinated with room users prior to the work taking place.

New end date for duration of impacts:

End Time / Date:      03:00 PM, Friday, July 26, 2024

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Updated 04/05/2024:  Please note that the end time and date for the project have been extended. However, all other previously communicated information remains unchanged. Any work within specific occupied space will continue to be coordinated with room users prior to the work taking place.

New end date for duration of impacts:

End Time / Date:      03:00 PM, Friday, April 12, 2024

For more details about this impact, please visit the website.  This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.

Original Notification (Published 03/27/2024):

Impact notification:

To: Engineering Building Users

From:    Sarah Abdellatif, Substation A Communication Specialist/Program Analyst

Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Setting up temporary power within rooms 101E, 103, 103B, 103C, 104, 118, 118A, 119, 122B, 123A, 130, 132A, 202G, 325.

Reason for Project: Preliminary work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Work associated with setting up temporary power will necessitate construction personnel to occupy rooms 101E, 103, 103B, 103C, 104, 118, 118A, 122B, 123A, 130, 132A, 202G, 325 throughout the duration of work. Please be advised that work will result in localized dust and noise, but there are no anticipated impacts to any building systems. 

Start Time / Date: 06:00 AM, Monday, April 1, 2024

End Time / Date: 03:00 PM, Friday, April 5, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please click here. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.