Please be advised that Planning, Design & Construction will be performing a project that may impact you. Below are the details of the scope of work and anticipated impacts:

Scope of Work: Pull electrical cables in preparation for building electrical upgrades.

Reason for Project: Preliminary work associated with the Electrical Infrastructure Upgrades project in support of current campus needs and future growth.

Anticipated Impacts: Medium voltage cable pulling work will limit vehicular access on the Northern end of Aztec Circle Drive to the West lane throughout the duration of work. Vehicular thru-traffic will be maintained by flagmen directing traffic in alternating directions and alternate pedestrian/accessible paths will be delineated by signage, flagmen and traffic control. Access to COGEN and Facilities Services through the East end of the driveway will be limited to small trucks and cars, with all other vehicle access maintained through the West end of the Driveway. Please be advised that work will result in localized dust and noise.

Start Time / Date: 06:30 AM, Monday, January 15, 2024 

End Time / Date: 03:00 PM, Friday, January 19, 2024

Contact:  Please direct any questions or concerns to Sarah Abdellatif, Substation A Communication Specialist/Construction Program Analyst at (858) 888-3215 or [email protected]. For questions about health and safety measures, please contact Gillian Marks, Senior Director of Environmental Health & Safety at (619) 594-2853 or [email protected].

For more details about this impact, please click here. This notification along with all other notices regarding the Electrical Infrastructure Upgrades (EIU) Project will be posted and archived for ease of reference on the EIU website.